See Orange Line Work We Completed October 4 – 6

Updated on October 18, 2019

A crew works on track replacement at Downtown Crossing during the October  4 - 6, 2019, weekend shutdown.
A crew works on track replacement at Downtown Crossing during the October 4 - 6, 2019, weekend service shutdown.

During 6 Orange Line weekend shutdowns, we close a section of track from Tufts to Sullivan so crews can bring vehicles and equipment into the central subway tunnel.

These service shutdowns allow our crews to complete work on 2 projects simultaneously—Orange Line Maintenance and Station Brightening—without requiring major long-term service closures. We’re also able to complete this work 11 months earlier than planned.

We thank you for your patience during these closures.

Learn more about Orange Line service changes

Building a Better T

As part of our $9.6 billion, 5-year capital investment plan, we're renovating stations, modernizing fare collection systems, upgrading services for our buses, subways, and ferries, and improving the accessibility of the entire system.

Learn more

Weekend 1: What We Completed

During the first weekend shutdown, our crews replaced 210 feet of track on the northbound side at Downtown Crossing and also replaced the flooring on 2 elevators at Chinatown.

We also:

  • Installed 8,000 feet of optic cable
  • Painted track and platform areas on State’s southbound side
  • Cleaned platform walls, ceilings, and floors on Haymarket’s southbound side
  • Cleaned track and platform walls and ceilings on Chinatown’s northbound side
  • Repaired leaks between Haymarket and State

Photo Gallery

Related Updates

Related Projects

View all projects

Building a Better T

As part of our $9.6 billion, 5-year capital investment plan, we're renovating stations, modernizing fare collection systems, upgrading services for our buses, subways, and ferries, and improving the accessibility of the entire system.

Learn more

Related Projects

View all projects