Codman Yard Construction Update | January 18 – February 7, 2025
Updated on January 24, 2025
Construction activities are ongoing for the Codman Yard Expansion and Improvements project. Construction is 40% complete.
Building a Better T
As part of our $9.6 billion, 5-year capital investment plan, we're renovating stations, modernizing fare collection systems, upgrading services for our buses, subways, and ferries, and improving the accessibility of the entire system.
Construction Progress Update
- Over the next three weeks, crews will work on track installation, electrical conduits, and the utility bridge.
- Pest management is ongoing.
- Traffic management occurs daily.
- Construction is expected on weekdays, 7 AM – 3 PM.
Download the construction update (PDF, 396 KB)